Which are NOT appropriate topics for discussion in a Sprint Retrospective? Choose 2 answers

A) Team accomplishments
B) Process improvements
C) Individual performance
D) Team collaboration

User Maxim Kim
by
8.5k points

1 Answer

6 votes

Final answer:

In a Sprint Retrospective, the topics that are not appropriate for discussion are individual performance as well as other issues not related to teamwork or process improvement. This is because the Retrospective focuses on the team as a unit and aims to foster a collaborative environment for process betterment.

Step-by-step explanation:

In a Sprint Retrospective, which is part of the Scrum framework, certain topics are considered more appropriate than others. The purpose of a Sprint Retrospective is to discuss the process and how the team can work better together in the future. As such, individual performance (C) and matters that are not directly related to the team’s collaboration or process improvements, such as process unrelated discussion points would generally be deemed inappropriate.

Therefore, the answer to which topics are NOT appropriate for discussion in a Sprint Retrospective would be C) Individual performance and another option that is not specified in the given list, since options A) Team accomplishments, B) Process improvements, and D) Team collaboration are typically considered relevant topics for discussion in a retrospective. The retrospective focuses on the team as a whole, and individual performance assessment can be counterproductive or uncomfortable within this group setting, as it might inhibit openness and collaboration.