223k views
2 votes
Group Assignment II

Question1: Project Management: Net work Models
The RELIABLE CONSTRUCTION COMPANY has just made the winning bid of $5.4 million to construct a new plant for a major manufacturer. The manufacturer needs the plant to go into operation within a year. Therefore, the contract includes the following provisions:
• A penalty of $300,000 if Reliable has not completed construction by the deadline 47 weeks from now.
• To provide additional incentive for speedy construction, a bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.
Reliable is assigning its best construction manager to this project to help ensure that it stays on schedule. The project manager looks forward to the challenge of bringing the project in on schedule, and perhaps even finishing early. However, since he is doubtful that it will be feasible to finish within 40 weeks without incurring excessive costs, he has decided to focus his initial planning on meeting the deadline of 47 weeks. The following tables show the list of the various activities and cost related information.
Table 1. Activity related information
Activity
Activity description
Immediate Predecessor
Estimated duration in weeks

A
Evacuate
-
2

B
Lay the foundation
A
4

C
Put up the rough wall
B
10

D
Put up the roof
C
6

E
Install the exterior plumbing
C
4

F
Install the interior plumbing
E
5

G
Put up the exterior sliding
D
7

H
Do the exterior painting
E,G
9

I
Do the electric work
C
7

J
Put up the wallboard
F,I
8

K
Install the flooring
J
4

L
Do the interior painting
J
5

M
Install the exterior fixtures
H
2

N
Install the interior fixtures
K,L
6





Given all the information in the two tables above and other information, answer the following questions.
1. Draw Network Diagram using AOA (Activity on Arrow) convention.
2. What is expected project duration and Identify critical activities?
4. Which are the critical bottleneck activities where any delays must be avoided to prevent
delaying project completion?
5. For the other activities, how much delay can be tolerated without delaying project completion?
7. Given the uncertainties in accurately estimating activity durations, what is the probability
of completing the project by the deadline?
8. Prepare the project crashing Schedule
9. Do you think Reliable enjoy the incentive or bear the penalty? Why?
Question2
Discuss on Inventory models (both dependent and independent) and support the models with examples.
Question 3
Solve the following problem
a. Using Branch and Bound and enumeration Method,
Zmin = 15x1 + 10x2 +12x3
S. To:
4x1 + 6x2 + 5x3 > 60
3x1 + x2 + x3 > 18
All variables > 0 and integer
b. How would the solution in (a) above vary if the problem were Binary.
Question 4
Discuss about simulation models and situations in which they could be applicable. Discuss also about Monte Carlo Model of Simulation Models.
Question 5.
What are main components of waiting/queuing lines model and where do you think these models could be applicable.

2 Answers

0 votes

1. Reliable Construction faces a $300,000 penalty if the new plant isn't completed in 47 weeks but stands to gain a $150,000 bonus if finished within 40 weeks.

2. The critical path includes activities A, B, C, D, G, H, J, K, and must be closely monitored to prevent delays.

3. Crashing the schedule may be necessary to meet the tight deadline, but Reliable should aim for completion within 40 weeks to secure the bonus.

4. Inventory models like EOQ and JIT are vital for managing stock, while simulation models, such as Monte Carlo, are applied in various industries to simulate complex systems and analyze uncertainties.

Question 1: Project Management: Network Models

1. Draw Network Diagram using AOA (Activity on Arrow) convention:

- The diagram cannot be drawn in this text-based format, but I can describe the sequence of activities and their dependencies.

- Activities: A, B, C, D, E, F, G, H, I, J, K, L, M, N

- Immediate Predecessor:

- A: -

- B: A

- C: B

- D: C

- E: C

- F: E

- G: D

- H: E, G

- I: C

- J: F, I

- K: J

- L: J

- M: H

- N: K, L

2. What is the expected project duration, and Identify critical activities:

- Expected project duration: The total time along the critical path

- Identify critical activities: Those activities on the critical path (with zero slack)

4. Which are the critical bottleneck activities where any delays must be avoided to prevent delaying project completion?

- Critical bottleneck activities are those on the critical path. In this case, activities with zero slack: A, B, C, D, G, H, J, K

5. For the other activities, how much delay can be tolerated without delaying project completion?

- Slack is the amount of time an activity can be delayed without delaying the project. For activities not on the critical path, you can find slack by subtracting the early start time from the late start time or early finish time from the late finish time.

7. Given the uncertainties in accurately estimating activity durations, what is the probability of completing the project by the deadline?

- This would require probabilistic time estimates for activities and the use of techniques like PERT (Program Evaluation and Review Technique) to calculate the probability of completing the project by the deadline.

8. Prepare the project crashing Schedule:

- Crashing involves shortening the duration of a project by reducing the time it takes to complete certain activities.

9. Do you think Reliable enjoys the incentive or bears the penalty? Why?

- Reliable should aim to complete the project within 40 weeks to enjoy the $150,000 bonus. If they exceed 47 weeks, they will incur a $300,000 penalty.

Question 2: Inventory Models (Dependent and Independent)

Dependent Inventory Model Examples:

- Just-In-Time (JIT)

- Material Requirements Planning (MRP)

Independent Inventory Model Examples:

- Economic Order Quantity (EOQ)

- Reorder Point (ROP)

Question 3: Linear Programming Problem

ion Method:

- The problem is missing the objective function coefficients for \(x_1\), \(x_2\), and \(x_3\).

- The constraints are \(4x_1 + 6x_2 + 5x_3 > 60\) and \(3x_1 + x_2 + x_3 > 18\).

- The solution would involve applying the Branch and Bound method and enumeration method once the objective function is complete.

b. How would the solution in (a) above vary if the problem were Binary:

- The solution approach would change as binary programming involves variables taking binary (0 or 1) values. This often requires specialized solution methods.

Question 4: Simulation Models

Simulation Models Applicability:

- Used in situations where real-world systems are complex or expensive to replicate.

- Common in manufacturing, finance, healthcare, and logistics.

Monte Carlo Model:

- A statistical method used in simulation models to account for uncertainty.

- Involves running multiple simulations with random input values to analyze the behavior of the system.

Question 5: Waiting/Queuing Lines Model

Main Components:

- Arrival process

- Service process

- Queue discipline

- Service facility

- Exit process

Applicability:

- Applicable in various industries, such as healthcare (patient queues), telecommunications (call centers), and transportation (traffic flow).

User Parviz Karimli
by
7.9k points
2 votes

Answer:

Group Assignment II

Question1: Project Management: Net work Models

The RELIABLE CONSTRUCTION COMPANY has just made the winning bid of $5.4 million to construct a new plant for a major manufacturer. The manufacturer needs the plant to go into operation within a year. Therefore, the contract includes the following provisions:

• A penalty of $300,000 if Reliable has not completed construction by the deadline 47 weeks from now.

• To provide additional incentive for speedy construction, a bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.

Reliable is assigning its best construction manager to this project to help ensure that it stays on schedule. The project manager looks forward to the challenge of bringing the project in on schedule, and perhaps even finishing early. However, since he is doubtful that it will be feasible to finish within 40 weeks without incurring excessive costs, he has decided to focus his initial planning on meeting the deadline of 47 weeks. The following tables show the list of the various activities and cost related information.

Table 1. Activity related information

Activity

Activity description

Immediate Predecessor

Estimated duration in weeks

A

Evacuate

-

2

B

Lay the foundation

A

4

C

Put up the rough wall

B

10

D

Put up the roof

C

6

E

Install the exterior plumbing

C

4

F

Install the interior plumbing

E

5

G

Put up the exterior sliding

D

7

H

Do the exterior painting

E,G

9

I

Do the electric work

C

7

J

Put up the wallboard

F,I

8

K

Install the flooring

J

4

L

Do the interior painting

J

5

M

Install the exterior fixtures

H

2

N

Install the interior fixtures

K,L

6

Given all the information in the two tables above and other information, answer the following questions.

1. Draw Network Diagram using AOA (Activity on Arrow) convention.

2. What is expected project duration and Identify critical activities?

4. Which are the critical bottleneck activities where any delays must be avoided to prevent

delaying project completion?

5. For the other activities, how much delay can be tolerated without delaying project completion?

7. Given the uncertainties in accurately estimating activity durations, what is the probability

of completing the project by the deadline?

8. Prepare the project crashing Schedule

9. Do you think Reliable enjoy the incentive or bear the penalty? Why?

Question2

Discuss on Inventory models (both dependent and independent) and support the models with examples.

Question 3

Solve the following problem

a. Using Branch and Bound and enumeration Method,

Zmin = 15x1 + 10x2 +12x3

S. To:

4x1 + 6x2 + 5x3 > 60

3x1 + x2 + x3 > 18

All variables > 0 and integer

b. How would the solution in (a) above vary if the problem were Binary.

Question 4

Discuss about simulation models and situations in which they could be applicable. Discuss also about Monte Carlo Model of Simulation Models.

Question 5.

What are main components of waiting/queuing lines model and where do you think these models could be applicable

User Taylor Riggan
by
8.5k points