Final answer:
The 'Develop Schedule' process belongs to the Planning process group in project management.
Step-by-step explanation:
The 'Develop Schedule' process belongs to the Planning process group in project management.
The Planning process group consists of processes that establish the scope of the project, define objectives, and plan the actions needed to reach those objectives. 'Develop Schedule' is one of the processes within this group.
This process involves analyzing project activities, their dependencies, and estimating the duration of each activity to create a comprehensive project schedule.