Final answer:
The total cost of the Flores job at Stanley Company, including the original installation and additional rework due to spoilage, is $5,970. This accounts for both initial and rework costs of direct materials, direct labor, and overhead applied at 160% of the direct labor cost.
Step-by-step explanation:
To calculate the total cost of the Flores job for Stanley Company, we need to factor in both the initial costs and the costs incurred due to the rework of the spoiled countertop.
- Initial direct materials: $2,600
- Initial direct labor: $700
- Rework direct materials: $900
- Rework direct labor: $250
Overhead is applied at 160% of direct labor cost. So, the initial overhead is 160% of the initial labor cost, and the overhead for rework is 160% of the rework labor cost.
- Initial overhead: 160% of $700 = $1,120
- Rework overhead: 160% of $250 = $400
Adding these costs together gives us the total cost for the Flores job:
- Total initial costs: $2,600 (direct materials) + $700 (direct labor) + $1,120 (overhead) = $4,420
- Total rework costs: $900 (direct materials) + $250 (direct labor) + $400 (overhead) = $1,550
- Total cost of Flores job: $4,420 (initial) + $1,550 (rework) = $5,970