For which of the following examples would it be best to use a predictive, plan-driven project management approach? Development of a flying car

Construction of a new office building
Research and development to discover a cure for the common cold
Creation of a new fashion line for the upcoming season

User Afri
by
8.6k points

1 Answer

4 votes

Final answer:

The construction of a new office building is best suited for a predictive, plan-driven project management approach due to the project's stable nature, need for detailed planning, and requirement for coordination, making it manageable with structured plans and controlled changes.

Step-by-step explanation:

For the question, 'For which of the following examples would it be best to use a predictive, plan-driven project management approach?', the best option to use a predictive, plan-driven project management approach would be the 'Construction of a new office building'.

This type of approach is well-suited for projects that are stable, well understood, and have clearly defined requirements. Projects in construction often require detailed planning, accurate cost estimation, and coordination between different disciplines, which are hallmarks of the predictive, plan-driven approach.

The approach ensures that the project is well structured and changes are carefully managed, which is essential in construction where deviations can be costly. On the other hand, the development of a flying car, the research and development to discover a cure for the common cold, or the creation of a new fashion line would require more flexibility and adaptability, making them better suited for agile or iterative project management methodologies.