The documented start and finish dates of activities, actual costs and durations, percent of work physically completed would all be considered ______.

1) Work performance information
2) Work performance data
3) Work performance inputs
4) Work performance reports

1 Answer

3 votes

Final answer:

Documented start and finish dates, actual costs, durations, and percent of work completed are considered work performance information, a term used in project management to monitor project progress.

Step-by-step explanation:

The documented start and finish dates of activities, actual costs and durations, percent of work physically completed would all be considered work performance information. This is the second option in the list you provided. Work performance information is essential for managing and controlling a project because it provides detailed insights into how the project is performing against the project management plan. This term is typically used within the context of project management to describe the detailed status of the project's progress, which includes metrics and other information that indicate how resources are being utilized to achieve project objectives.

User Sasha Zezulinsky
by
8.3k points