Which of the following is not a trigger situation for updating the stakeholder management plan?

1) Changes in project scope
2) Changes in project schedule
3) Changes in project budget
4) Changes in project team members

User Omilus
by
7.9k points

1 Answer

3 votes

Final answer:

Changes in project team members are not a trigger situation for updating the stakeholder management plan.

Step-by-step explanation:

Changes in project team members are not a trigger situation for updating the stakeholder management plan.

A stakeholder management plan outlines how an organization will engage and communicate with the individuals or groups who have an interest in or may be affected by the project.

While changes in project scope, schedule, and budget can all impact stakeholders and may require updates to the stakeholder management plan, changes in project team members do not necessarily impact stakeholder management directly.