124k views
4 votes
Activities on the critical path are critical because they:

A) Represent the maximum project completion time
B) Cannot tolerate any delay in completion
C) Represent the most expense in terms of resources
D) Represent the largest and most complex activities of the project

User Zavior
by
6.6k points

1 Answer

5 votes

Final answer:

Activities on the critical path cannot tolerate any delay because they define the minimum time to complete a project. Any delay affects the project's completion date, potentially causing missed business opportunities and loss of revenue.

Step-by-step explanation:

Activities on the critical path are critical because they: B) Cannot tolerate any delay in completion. This is because the critical path represents the sequence of tasks that dictate the minimum amount of time necessary to complete the project. Any delay in these tasks will directly affect the project completion date.

In the context of engineering and product development, such as designing a new video game controller, adherence to the critical path is crucial. Missing deadlines on critical tasks could mean missing significant business opportunities, like the holiday sales season, or being outpaced by competitors. Therefore, project managers and team members must closely monitor and manage tasks on the critical path to ensure timely delivery.

User Nijikokun
by
8.3k points