Final answer:
The statement about the DD Form 441 being executed at the time of contract award is false. This form establishes a security agreement and may be executed before the contract award if the project requires access to classified information.
Step-by-step explanation:
The statement "A Security Agreement (DD Form 441) is executed at the time of contract award." is False.
The DD Form 441, also known as the Department of Defense (DoD) Security Agreement, is not necessarily executed at the time of contract award. This form is used to establish a security agreement between a government contractor and the DoD, outlining the security responsibilities of the contractor.
It is part of the process of gaining facility clearance (FCL), which allows companies to access classified information. The execution of DD Form 441 can be required before contract award if the work to be performed requires access to classified information.
However, the timing of its execution may vary, and it might be executed well before the actual contract award depending on the security requirements and the process of ensuring the contractor's facility is cleared for handling sensitive information.