Which of the following is a true statement regarding the V-model life cycle?

A. Testing involvement starts when the code is complete
B. The test process is integrated with the development process
C. The software is built in increments and each increment has activities for requirements, design,build and test
D. All activities for development and test are completed sequentially

User Natoya
by
7.4k points

1 Answer

2 votes

Answer:

The true statement about the V-model life cycle is that the test process is integrated with the development process, leading to simultaneous testing and development activities rather than sequential completion of each phase. Therefore, the correct multiple-choice option is (B).

Step-by-step explanation:

The V-model life cycle is a conceptual framework used in software development that represents processes that should occur sequentially during the software development life cycle. Unlike traditional sequential design models, which do not fully integrate testing until after completion of development, the V-model emphasizes the importance of testing at each stage in the development process. This means that for each development activity, there is a corresponding testing activity. Thus, testing in the V-model is integrated within the development process and begins much earlier than in traditional models like the waterfall model.

Correct answer to the student's question

The true statement regarding the V-model life cycle is: B. The test process is integrated with the development process. This integration helps in identifying issues early on in the development process, thus facilitating a more efficient and effective design and development cycle. It is an iterative process that includes refining the design upon evaluation of the prototypes. Therefore, the correct multiple-choice option is (B).