The __________ process involves performing the project closure portion of the project management plan.

A Perform Integrated Change Control
B Execute Closure
C Close Project or Phase
D Develop Project Charter

User Miz
by
7.5k points

1 Answer

1 vote

Final answer:

The correct answer is C. Close Project or Phase.

Step-by-step explanation:

The correct answer is C. Close Project or Phase. In project management, the closing process involves finalizing all activities and completing all necessary paperwork to formally close a project or phase. This includes conducting a final review, obtaining project sign-off, and archiving project documents.