Final answer:
The document that does not usually get included in the project scope statement is (Option 2)the Work Breakdown Structure (WBS). The project scope statement includes project assumptions, constraints, product description, and project deliverables.
Step-by-step explanation:
The project scope statement is an essential document in project management that outlines the work required to complete a project. It typically includes several elements such as project assumptions, constraints, product description, and project deliverables. However, it does not usually include the Work Breakdown Structure (WBS). The WBS is a separate document that decomposes the project into smaller, more manageable pieces, and is used for developing the project schedule and assigning responsibilities.
When answering which of the following is not included in the project scope statement, the correct answer is option 2, the WBS. Key aspects of project management, such as the importance of a well-defined project scope, the role of the WBS, and the purpose of deliverables, illustrate how different aspects of a project are managed and documented.
When considering the quality of a design, the engineering design process can be used. This process focuses on the attributes of the product and involves testing prototypes, though it is not directly included in the project scope but is essential for product development.