Final answer:
The question calculates the cost to be transferred to Finished Goods by adding the actual labor, materials, and overhead costs, resulting in a total of $1,085,000 for Job No. 51.
Step-by-step explanation:
The question asks for the amount transferred to Finished Goods when actual costs differ from expected costs. To calculate this, we need to add up the actual costs of labor, materials, and overhead that were incurred during the production process. The sum of these costs is the total manufacturing cost that will be transferred to the Finished Goods account.
The actual costs were:
- Labor Cost: $220,000
- Materials Used: $570,000
- Overhead Cost: $295,000
Adding these together, the transfer to Finished Goods would be:
Labor ($220,000) + Materials ($570,000) + Overhead ($295,000) = $1,085,000