Final answer:
The coefficient of variation for the project is calculated by dividing the standard deviation (30%) by the expected return (24%), resulting in a coefficient of variation of 1.25. Therefore, the correct answer is option a. 1.25.
Step-by-step explanation:
The question is asking to calculate the coefficient of variation for a given project which has an expected return of 24% and a standard deviation of 30%. The coefficient of variation (CV) is a statistical measure of the dispersion of data points in a data series around the mean. It is calculated as the ratio of the standard deviation to the mean. In this case, to find the CV for the project:
CV = Standard Deviation / Expected Return
CV = 0.30 / 0.24
CV = 1.25
Therefore, option a. 1.25 is the correct answer.