Final answer:
The total cost of Job 20 for the Daffodil Company is calculated by adding the beginning balance, materials requisitioned, direct labor cost, and overhead. After calculating these amounts, the total cost is $8,600, which does not match any of the provided answer options.
Step-by-step explanation:
To calculate the total cost of Job 20 for the Daffodil Company, a manufacturing company that produces a wide variety of products, we need to sum up the beginning balance, the cost of materials requisitioned, direct labor cost, and the overhead assigned. The overhead is given as 60 percent of the direct labor cost. Here's the calculation:
Adding these amounts together gives us the total cost of Job 20:
$500 (Beginning balance) + $4,500 (Materials) + $2,250 (Direct labor) + $1,350 (Overhead) = $8,600
However, none of the provided options (a) $9,750 (b) $10,200 (c) $12,750 (d) $11,250 match this calculated total cost of $8,600. It looks like there may be an error with the provided options or the calculations.