Final answer:
The NPV for Plan A is approximately $85.62 million and the IRR is approximately 13.67%. The NPV for Plan B is approximately $20.72 million and the IRR is approximately 11.90%.
Step-by-step explanation:
To calculate the NPV of each project, we need to determine the present value of the expected cash flows for each year. Using the formula:
NPV = Cash Flow / (1 + WACC)^n
where WACC is the weighted average cost of capital and n is the number of years. For Plan A, the NPV can be calculated as follows:
Year 1: $6.23 million / (1 + 0.09)^1 = $5.72 million
Year 2: $6.23 million / (1 + 0.09)^2 = $5.25 million
Year 20: $6.23 million / (1 + 0.09)^20 = $0.89 million
Summing up all the present values, the NPV for Plan A is approximately $85.62 million.
Similarly, for Plan B:
Year 1: $2.69 million / (1 + 0.09)^1 = $2.47 million
Year 2: $2.69 million / (1 + 0.09)^2 = $2.27 million
Year 20: $2.69 million / (1 + 0.09)^20 = $0.38 million
The NPV for Plan B is approximately $20.72 million.
To calculate the IRR for each project, we need to find the discount rate that makes the NPV equal to zero. Using Excel, we can find the IRR for Plan A, which is approximately 13.67%. Similarly, for Plan B, the IRR is approximately 11.90%