Final answer:
The NPV of this project is $62,997.60. The company should buy and install the machine press.
Step-by-step explanation:
To calculate the NPV of the project, we need to determine the cash flows, discount them to the present value, and then subtract the initial investment. The cash flows consist of the annual pretax cost savings and the salvage value at the end of the project. To calculate the annual pretax cost savings, we subtract the annual inventory costs from the savings. The annual inventory costs are the initial inventory cost plus the additional inventory costs for each succeeding year. We can then calculate the net cash flow for each year by multiplying the annual pretax cost savings by (1-tax rate). After determining the net cash flows, we discount them to the present value using the discount rate. Finally, we subtract the initial investment to get the NPV.
Net Cash Flow = [(Annual Pretax Cost Savings - Annual Inventory Costs) - (Annual Pretax Cost Savings - Annual Inventory Costs) * Tax Rate]
Discounted Cash Flow = Net Cash Flow / (1 + Discount Rate)^(Year - 1)
NPV = Sum of Discounted Cash Flows - Initial Investment
Calculating the NPV of the project:
- Year 1: Net Cash Flow = [($157,000 - $24,000) - ($157,000 - $27,300) * 0.24] = $126,870, Discounted Cash Flow = $126,870 / (1 + 0.11)^(1 - 1) = $126,870, NPV = $126,870 - $405,000 = $-278,130
- Year 2: Net Cash Flow = [($157,000 - $27,300) - ($157,000 - $30,600) * 0.24] = $126,750, Discounted Cash Flow = $126,750 / (1 + 0.11)^(2 - 1) = $114,148.65, NPV = $114,148.65 - $0 = $114,148.65
- Year 3: Net Cash Flow = [($157,000 - $30,600) - ($157,000 - $33,900) * 0.24] = $126,630, Discounted Cash Flow = $126,630 / (1 + 0.11)^(3 - 1) = $99,341.57, NPV = $99,341.57 - $0 = $99,341.57
- Year 4: Net Cash Flow = [($157,000 - $33,900) - ($157,000 - $37,200) * 0.24] = $126,510, Discounted Cash Flow = $126,510 / (1 + 0.11)^(4 - 1) = $86,247.20, NPV = $86,247.20 - $0 = $86,247.20
- Salvage Value: Net Cash Flow = $57,000 * (1 - 0.24) = $43,320, Discounted Cash Flow = $43,320 / (1 + 0.11)^(4 - 1) = $31,390.18, NPV = $31,390.18 - $0 = $31,390.18
- NPV = Sum of Discounted Cash Flows - Initial Investment = ($126,870 + $114,148.65 + $99,341.57 + $86,247.20 + $31,390.18) - $405,000 = $62,997.60
The NPV of this project is $62,997.60. Since the NPV is greater than zero, the company should buy and install the machine press.