One way to schedule a project is for activity A to have a duration of six weeks and for activity B to have a finish-to-start (FS) relationship to it and a duration of four weeks. Another way would be to have activity B have a SS+2 relationship to activity A. Assuming both options are somehow feasible, what is the advantage of the second method?

User Atrotors
by
6.7k points

1 Answer

6 votes

Final Answer:

The advantage of the second method, where activity B has a SS+2 relationship to activity A, lies in its increased flexibility and potential for parallelism in project execution.

Step-by-step explanation:

In the second method with the SS+2 relationship, activity B starts two weeks after activity A begins, allowing for a potential overlap or parallel execution. This enables the project manager to exploit a window of opportunity, potentially shortening the overall project duration.

Moreover, the SS+2 relationship provides more room for adjustments. If activity A encounters delays within its six-week duration, the SS+2 relationship allows activity B to start later, reducing the impact of the delay and potentially keeping the project on track.

Furthermore, the SS+2 approach offers a more adaptable schedule. It provides leeway for optimizing resources, as resources allocated for activity A can potentially be reallocated or shared during the two-week gap before activity B commences.

Additionally, this method enhances risk mitigation. If unforeseen challenges arise during activity A, the SS+2 relationship allows for a buffer period before activity B begins, providing a cushion to address issues without immediately impacting subsequent tasks.

Lastly, the SS+2 relationship promotes a more efficient use of resources by potentially allowing activities A and B to run partially in parallel, maximizing productivity and potentially accelerating the project's completion.

In summary, the advantage of the second method lies in its flexibility, adaptability, risk mitigation, resource optimization, and potential for parallel execution, offering a more robust approach to project scheduling.