Final answer:
The net present value (NPV) of the project is $1,310,580, which is positive. Therefore, the project should be implemented as it is expected to generate a positive return and exceed the required rate of return.
Step-by-step explanation:
To determine whether the project should be implemented, we need to calculate the net present value (NPV) of the project. The NPV is the sum of the present values of all cash inflows and outflows over the life of the project.
First, let's calculate the net cash flows for each year:
- Year 0: -Capex = -$2 million
- Years 1-10: Annual savings in operating costs = $600,000
- Year 10: Sale of equipment = $500,000
Next, let's calculate the present value of each cash flow using a discount rate of 12%:
- Year 0: PV = -$2 million / (1 + 0.12)^0 = -$2 million
- Years 1-10: PV = $600,000 / (1 + 0.12)^n where n is the year
- Year 10: PV = $500,000 / (1 + 0.12)^10 = $185,270
Finally, let's sum up the present values:
- NPV = PV of cash inflows - PV of cash outflows = $600,000 * (1 - (1 + 0.12)^-10) / 0.12 - $2 million + $185,270 = $1,310,580
Since the NPV is positive ($1,310,580), the project should be implemented as it is expected to generate a positive return and exceed the required rate of return.