Final answer:
Top-down scheduling is the method where a project manager reviews all individual tasks and rolls them into manageable chunks that lead to a milestone.
Step-by-step explanation:
The correct method where a project manager reviews all individual tasks and rolls them into manageable chunks that lead to a milestone is top-down scheduling. Top-down scheduling involves starting with the overall goal or milestone and breaking it down into smaller tasks or subgoals.
For example, let's say a project manager is tasked with organizing a conference. The top-down scheduling approach would involve first identifying the main objectives of the conference, such as finding a venue, securing speakers, and creating a schedule. These main objectives are then further broken down into smaller tasks, such as researching potential venues, reaching out to potential speakers, and creating a detailed agenda. This hierarchical approach helps ensure that all tasks are aligned with the overall goal and milestone.
Top-down scheduling is an effective method for project management as it provides a clear structure and helps prioritize tasks. It allows for better coordination and control of the project, as well as identifying any potential issues or challenges early on.