Final answer:
The yearly total material handling cost for the current layout in Plan A of the Missouri job shop is $60,500.
Step-by-step explanation:
To calculate the yearly total material handling cost of the current layout presented in Plan A for a Missouri job shop with departments machining (M), dipping in a chemical bath (D), finishing (F), and plating (P), we must consider the number of workpieces moved yearly between departments and the distance between these work areas in feet. The cost of moving one workpiece one foot is $1.00.
- From M to D: 800 workpieces × 21 feet = 16,800 dollars
- From M to F: 2,000 workpieces × 13 feet = 26,000 dollars
- From M to P: 400 workpieces × 9 feet = 3,600 dollars
- From D to F: 400 workpieces × 7 feet = 2,800 dollars
- From D to P: 300 workpieces × 11 feet = 3,300 dollars
- From F to P: 2,000 workpieces × 4 feet = 8,000 dollars
Adding these figures up: 16,800 + 26,000 + 3,600 + 2,800 + 3,300 + 8,000 dollars equals 60,500 dollars. This represents the yearly total material handling cost for the current layout in Plan A.