Final answer:
In 15 months with specialization, Carla's and June's teams combined will build 8 single-family homes; 5 by Carla's team and 3 by June's team.
Step-by-step explanation:
The question asks how many single-family homes will be built in 15 months by Carla's and June's teams, assuming they specialize in this project type. Carla's team can build a single-family home in 3 months, and June's team can build one in 4.5 months. If both teams specialize exclusively in single-family homes, in 15 months:
Carla's team will build 15 months / 3 (months/home) = 5 homes.
June's team will build 15 months / 4.5 (months/home) = approximately 3.33 homes, but since you can't build a fraction of a home in this context, we'll assume they only complete 3 homes.
Therefore, combined, the teams will build 5 (Carla's team) + 3 (June's team) = 8 single-family homes.