Final answer:
The planned assessed level of control risk should be modified because the tolerable deviation rate plus the allowance for sampling risk exceeds the expected population deviation rate.
Step-by-step explanation:
The correct option is 1) The planned assessed level of control risk should be modified because the tolerable deviation rate plus the allowance for sampling risk exceeds the expected population deviation rate.
In this scenario, the tolerable deviation rate is 7 percent and the allowance for sampling risk is 2 percent, which gives a total of 9 percent. This value is higher than the expected population deviation rate of 5 percent. Therefore, the planned assessed level of control risk should be modified.