14.2k views
4 votes
A ______________is used when 90% to 100% of the construction documents (CDs) are completed.

1 Answer

3 votes

Final answer:

A punchlist is used when 90% to 100% of the construction documents (CDs) are completed. It is a document that identifies remaining work or quality issues that need to be addressed before final completion of a construction project.

Step-by-step explanation:

A punchlist is used when 90% to 100% of the construction documents (CDs) are completed.

A punchlist is a document that identifies any remaining work or quality issues that need to be addressed before final completion of a construction project. It is usually created by the architect or engineer and is used as a checklist for the contractor to fix any deficiencies or issues.

Learn more about Punchlist

User Canato
by
7.2k points