Final answer:
Resource allocation is typically not one of the items that define each milestone on the critical path in a PERT chart, which usually includes start time, duration, and dependencies.
Step-by-step explanation:
In project management, a PERT (Program Evaluation Review Technique) chart is a tool used to visualize and analyze the tasks involved in completing a project, especially the time required to complete each task and the order in which those tasks must be completed. When looking at the items that define each milestone on the critical path in a PERT chart, the options listed typically include:
- Start time
- Duration
- Dependencies
However, resource allocation is not usually one of the items that define a milestone on the critical path in a PERT chart. Resource allocation refers to the distribution of resources among various tasks or projects, and while it is an important aspect of project management, it is not a defining characteristic of a milestone in the context of a PERT chart which focuses more on the sequencing and scheduling of tasks.