an order for the end item is scheduled to be shipped at the start of week 11. what is the latest week that the order can be started an still be ready to ship on time? (hint: you don't need to develop an mrp plan for this part either.)

1 Answer

5 votes

The latest week that the order can be started and still be ready to ship on time is week 9, we need to consider the lead times for each component and the amount on hand.

In order to determine the latest week that the order can be started and still be ready to ship on time, we need to consider the lead times for each component and the amount on hand. We should start with the end item and work backwards through the components.

End Item

Lead Time: 2 weeks

Amount on Hand: 10

Based on the information provided, we can see that the end item has enough on hand to fulfill the order. Therefore, the latest week the order can be started and still be ready to ship on time is week 9.

--"The given question is incomplete, the complete question is given below:

an order for the end item is scheduled to be shipped at the start of week 11. what is the latest week that the order can be started an still be ready to ship on time? (hint: you don't need to develop an mrp plan for this part either.)

The following table lists the components needed to assemble an end item, lead times, and quantities on hand. G Item LT (week) Amount on hand End 1 B 2 10 C 3 10 D 3 25 E 1 12 ܗ ܝ F 2 30 ܘ ܝ ܗ ONI Click here for the Excel Data File End Item B (2) с D (3) E (2) F(3) G (2) E (2) H (4) E (2) a."--