Final answer:
The claim that the 'General Conditions' is the highest order of precedence document under the CMAA contract document A-3 is false. Typically, the 'Agreement' holds the highest order of precedence.
Step-by-step explanation:
The statement is False. In the Construction Management Association of America (CMAA) contract document A-3, General Conditions for Agency Construction Management, the contract documents order of precedence clause does not place the 'General Conditions' as the highest order of precedence document. Typically, the 'Agreement' holds the highest order of precedence, followed by other documents such as Supplementary Conditions, General Conditions, Division 1 General Requirements and Division 2 through 49 based on the specific project requirements and contract arrangement.
Learn more about CMAA Contract Document A-3