12.0k views
4 votes
What is the agile method of program development? (5 points) a Project teams do not keep documentation about the changes made to the project. b Project teams do not move on to the next step in the project before the previous step is completed. c Project teams do smaller portions of the entire project at the same time. d Project teams work on one step of the project at a time.

User Drew
by
7.8k points

1 Answer

4 votes
The correct answer is C. Project teams do smaller portions of the entire project at the same time.
User Nohemi
by
7.5k points