Nafth Company has an Equipment Services Department that performs all needed maintenance work on the equipment in the company's Fabrication and Assembly Departments. Costs of the equipment Services Department are charged to the Fabrication and Assembly Departments on the basis of direct labor-hours. Data on direct labor-hours for last year follow: Fabrication Assembly Total Budgeted direct labor-hours 20,000 50,000 70,000 Actual direct labor-hours 25,000 55,000 80,000 Peak-period direct labor-hours 30,000 70,000 100,000 For the year just ended, the company budgeted its variable maintenance costs at $210,000 for the year. Actual variable maintenance costs for the year totaled $255,000. For performance evaluation purposes, how much of the $255,000 of actual variable maintenance cost should be charged to the Assembly Department at the end of the year just ended?

User Alon Segal
by
8.0k points

1 Answer

0 votes

Answer:165000

Explanation:(Total budgeted cost/Total budgeted hours)* actual hours

User Red Hyena
by
6.8k points