Answer:
To determine the flexible budget for the Cutting Department, we need to use the information provided to adjust the original budget for the actual level of production.
First, we need to calculate the variable cost per hour of production:
Variable cost per hour = Direct labor / Hours of production
Variable cost per hour = $37,260 / 4,140 hours
Variable cost per hour = $9
Next, we can use this variable cost per hour to calculate the flexible budget for the actual level of production:
Flexible budget = (Variable cost per hour x Actual hours of production) + Fixed costs
Flexible budget = ($9 x 4,500 hours) + $43,370
Flexible budget = $40,500 + $43,370
Flexible budget = $83,870
Therefore, the flexible budget for the Cutting Department, based on the actual level of production of 4,500 hours, is $83,870.