129k views
5 votes
During the ceremony, a printing

company received a very large order to
carry out the production of campaign
material. It was estimated that the 3
machines would take 24 hours to
perform the entire service. Assuming
that one of these machines breaks
down before starting the service, how
long will it take to meet this demand?

User Tompee
by
7.5k points

1 Answer

3 votes

If one of the three machines breaks down before starting the service, it would take the remaining two machines longer to meet the demand. If each machine can produce the same amount of material, it would take each machine 24 hours / 3 machines = 8 hours to perform the entire service.

So, with two machines working, it would take each machine 8 hours / 2 machines = 4 hours to complete the job. Thus, the total time to meet the demand would be 4 hours * 2 machines = 8 hours.

User Virusrocks
by
7.7k points