It takes 15 people two hours to plant 450 tomatoes. If 5 more people are hired, how long will it take them to plant the same number of tomatoes?

1 Answer

3 votes
Let's call the number of people working as "p" and the time it takes as "t". We know that with 15 people, it takes 2 hours to plant 450 tomatoes, so we can write:

15 people * t = 450 tomatoes
t = 450 / 15 = 30 minutes = 0.5 hours

If 5 more people are hired, there will be a total of 15 + 5 = 20 people working. To find the new time it takes to plant 450 tomatoes, we can rearrange the formula to solve for t:

t = 450 / (15 + 5) = 450 / 20
t = 22.5 minutes = 0.375 hours

So, with 20 people, it will take 0.375 hours to plant 450 tomatoes