Given
Hourly rate of labor = $12.00
Duration of job = 3 1/2 hours
Overhead rate = 66 2/3%
Price of parts = $112.50
Answer
Rate for 3 1/2 hr =12 x 3 1/2 = 12 x 7/2 = $ 42
Overhead rate 66 2/3 % of $42 = 28
Total cost job = 112.50 + 28 + 42 = $182.50