Answer:
Option A is the correct answer.
Explanation:
Let the work be W.
Ram can complete the work in 10 hours, Ajit in 12 hours and Suresh in 15 hours.

Ram had to leave the work after 2 hours of the start and Ajit left 3 hours before the completion of the work.
Let t be the time of work completion,
We have

Option A is the correct answer.