Answer:
4 /3 or 1.33 hours
Step-by-step explanation:
The relationship between raking rate v, the time t and the distance to rake D is given by
The above can be solved for t to give
It takes brian 4 hours to rake the front lawn. Therefore,
solving for vb gives
It takes John two hours to take the same lawn. Therefore,
solving for vj gives
where
v_b = rate at which brian rakes
v_j = rate at which john rakes.
Now, if they both worked together, then their raking rate would be,
Therefore, the time it takes to rake the same lawn would be
Since we found that v_b = D / 4 and v_j = D /2, the above gives