Greg planned for his company to make $ 25,000 this month . Instead, they made $18,000 . Calculate the variance .

User Juhi
by
5.3k points

2 Answers

9 votes

Answer:

72%

Explanation:

18,000 / 25,000 = 72% variance. In other words, they made 72% less than they had projected.

User Alphy
by
5.2k points
10 votes

Answer:

The answer is $7,000