It takes Franklin 14 hours to make a 200-square-foot cement patio. It takes Scott 10 hours to make the same size patio. Which equation can be used to find x, the number of hours it would take Franklin
asked
Jul 26, 2015
214k
views
4
votes
It takes Franklin 14 hours to make a 200-square-foot cement
patio. It takes Scott 10 hours to make the same size patio. Which
equation can be used to find x, the number of hours it would take
Franklin and Scott to make the patio together?
Mathematics
high-school
Douglas Leeder
asked
by
Douglas Leeder
8.9k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
4
votes
F = Franklin (rate) = 200 ft² / 14 hrs = 200/14 ft²/hr = 14.2587 ft²/hr
S = Scott (rate) = 200 ft² / 10 hrs = 200/10 ft²/hr = 20 ft²/hr
Combined . . .
Fx + Sx = 200
(F + S)x = 200
x = 200/(F + S)
(F + S) = 200/14 + 200/10 = 2000/140 + 2800/140 = 4800/140 = 240/7
x = 200/(240/7)
x = 200/240*7 = 20/24*7 = 140/24 = 35/6
x = 35/6 hrs = 5 5/6 hrs = 5 hrs 50 min
Jeremy Murray
answered
Jul 28, 2015
by
Jeremy Murray
8.5k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
6
votes
Answer:
its C 1/14x+1/10x=1
Explanation:
just took on ED
Giorgio Tempesta
answered
Aug 1, 2015
by
Giorgio Tempesta
8.6k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
Related questions
asked
Aug 24, 2024
33.6k
views
It takes Franklin 14 hours to make a 200-square-foot cement patio. It takes Scott 10 hours to make the same size patio. Which equation can be used to find x, the number of hours it would take Franklin
Aquarhead
asked
Aug 24, 2024
by
Aquarhead
8.6k
points
Mathematics
high-school
1
answer
1
vote
33.6k
views
asked
Nov 6, 2024
216k
views
It takes Franklin 14 hours to make a 200-square-foot cement patio. It takes Scott 10 hours to make the same size patio. Which equation can be used to find x, the number of hours it would take Franklin
Eliego
asked
Nov 6, 2024
by
Eliego
8.8k
points
Mathematics
high-school
1
answer
1
vote
216k
views
asked
May 9, 2017
68.6k
views
It takes Franklin 14 hours to make a 200-square-foot cement patio. It takes Scott 10 hours to make the same size patio. Which equation can be used to find x, the number of hours it would take Franklin
Fateh Mohamed
asked
May 9, 2017
by
Fateh Mohamed
8.1k
points
Mathematics
high-school
1
answer
5
votes
68.6k
views
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.5m
questions
12.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Write words to match the expression. 24- ( 6+3)
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org