Refer to the table below. what is the cumulative budgeted cost at the end of week 6? amounts are in thousands of dollars.

User Splurk
by
9.0k points

1 Answer

2 votes
The cumulative budgeted cost at the end of week 6 is $100,000. The answer in this question whose are amounts are in thousand of dollars is $100,000. So, the cumulative budgeted cost at the end of the week 6 is $100,000.Cumulative budgeted cost or acronym of CBC is the amount that is budgeted in order to accomplish the work that was scheduled.