Final answer:
The direct labor cost budget for Pasadena Candle Inc. is $1,413,000 for the year, calculated from the 78,500 hours needed at $18 per hour. The direct material purchases for the wax needed are $604,035, based on 487,125 pounds of wax at $1.24 per pound.
Step-by-step explanation:
To calculate the direct labor cost budget for Pasadena Candle Inc., we must first find the total molding time required for production. With each candle taking six minutes to mold and the company planning to produce 785,000 candles, the total molding time will be:
- 785,000 candles × 6 minutes per candle = 4,710,000 molding minutes
Next, we convert molding minutes into hours since the labor cost is provided in dollars per hour.
- 4,710,000 minutes ÷ 60 minutes per hour = 78,500 molding hours
Then we calculate the total labor cost by multiplying the hours required by the cost per hour:
- 78,500 hours × $18 per hour = $1,413,000
The direct labor cost budget for molding the candles for the entire year will be $1,413,000.
For the direct material purchases, we must calculate the cost of the wax needed. With 487,125 pounds of wax required and a cost of $1.24 per pound, the calculation is:
- 487,125 pounds × $1.24 per pound = $604,035
The total direct material purchases for the wax needed to produce the candles will be $604,035.