Answer:
29 more workers are needed.
Explanation:
Let us assume that the 10 workers, working at their normal rate would finish the job in exactly 8 days.
The rate of working for 1 worker is:
[ 1/10 of the job ] / [ 8 days ] = [ 1 job ] / [ 80 days ]
This is also [ 1/80 of the job ] / [ 1 day ]
In 2 days, the fraction of the job that gets done is:

Job left =

Now the rate has to be :

Now, let w be the additional number of workers needed.
We get:

Solving for w;


w = 29
Therefore, 29 more workers are needed.
-------------------------------------------------------------------------------------
There can be another approach as well.
Fraction of the job done by 10 workers in 2 days = 1/4
Remaining fraction = 1-1/4 = 3/4
Lets say W workers are needed more.
So, we can say that 3/4 of the work is to be done by 10+W workers.
Hence, it will take a total of 30 workers to complete the job.
Making it additional 20 workers.