Working alone, Ryan can dig a 10 ft by 10 ft hole in five hours. Castel can dig the same hole in six hours. How long will it take them if they worked together? Explain too please, thanks.
asked
Jun 26, 2018
61.7k
views
2
votes
Working alone, Ryan can dig a 10 ft by 10 ft hole in five hours. Castel can dig the same hole in six hours. How long will it take them if they worked together?
Explain too please, thanks.
Mathematics
middle-school
Adam Patterson
asked
by
Adam Patterson
6.2k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
0
votes
x/5+x/6=1
6x+5x=30
11x=30
x=30/11
x=2 8/30 =2 8/30 hours
8/30 hr=16 minutes
2 hours 16 minutes.
Hope this helped.
Tularis
answered
Jun 27, 2018
by
Tularis
6.0k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
5
votes
.
Rates:
Ryan: 1 hole per 5 hours
Castel: 1 hole per 6 hours
.
Let x = time if working together
then
x(1/5 + 1/6) = 1
x(6 + 5) = 30
11x = 30
x = 30/11
x = 2.7273 hours
or
x = 2 hours and 44 minutes
Masiorama
answered
Jul 2, 2018
by
Masiorama
6.1k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
7.2m
questions
9.7m
answers
Other Questions
How do you estimate of 4 5/8 X 1/3
Write words to match the expression. 24- ( 6+3)
Please solve the following equation. x-6x=56
whats the most accurate estimation of 65+77
Find the additive inverse of 18/23
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org