t takes Franklin 14 hours to make a 200-square-foot cement patio. It takes Scott 10 hours to make the same size patio. Which equation can be used to find x, the number of hours it would take Franklin and
asked
Apr 8, 2018
131k
views
2
votes
t takes Franklin 14 hours to make a 200-square-foot cement patio. It takes Scott 10 hours to make the same size patio. Which equation can be used to find x, the number of hours it would take Franklin and Scott to make the patio together?
Mathematics
high-school
Rafael Pedrosa
asked
by
Rafael Pedrosa
6.6k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
5
votes
Answer:
c. 1/14x + 1/10x = 1
Explanation:
Heug
answered
Apr 9, 2018
by
Heug
6.8k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
6
votes
The efficiency of Franklin: 200/14 ft^2/hr
Scott: 200/10 ft^2/hr
So together: 200 / (200/14 + 200/10) = 5.83 hours
Abin Thaha
answered
Apr 14, 2018
by
Abin Thaha
7.5k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
8.3m
questions
10.9m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
Write words to match the expression. 24- ( 6+3)
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org