In July 1 2020 culver inc invested $635250 in a mine estimated to have 847000 tons of ore of uniform grade during the last 6 months of 2020 146000 tons of ore were mined calculate depletion cost per unit

User Jay Moorthi
by
2.8k points

1 Answer

16 votes
16 votes

Given:

culver inc invested $635250 in a mine estimated to have 847000 tons of ore of uniform grade

So, the estimated cost per unit =


(635250)/(847000)=0.75

This means the cost = $0.75 per ton