93.3k views
4 votes
a carpenter estimates that it will take one person 54 hours to complete a job he plans to have three people work on the job for two days how many hours each day will the workers need to work to complete the job

User Loneraver
by
6.3k points

1 Answer

7 votes
2 days = 54/2 = 27 hours a day
Your welcome
User Chathura Buddhika
by
6.3k points