If a project will take 35 employees 2,940 hours to complete, how many hours will each employee have to work? A. 45 B. 84 C. 76 D. 55

User Ludlow
by
7.8k points

2 Answers

4 votes
B because you have to do divide it
User Sabeen
by
8.8k points
2 votes
You take 2940 and divide it by 35.  That gives you 84 hours per employee 