79.0k views
4 votes
It takes 22 minutes for 10 people to paint 10 walls. How many minutes does it take 14 people to paint 14 walls?

User Irfan Wani
by
8.4k points

2 Answers

1 vote
220pm=10w (people*minutes)

w=22pm

14w=308pm

308pm/14p=22m

So it would take 22 minutes for 14 people to paint 14 walls.
User Kofi Sammie
by
8.0k points
3 votes

Answer: 22 minutes

Explanation:

Since, if
x_1 people take
n_1 days for doing
w_1 work while
x_2 people take
n_2 days for doing
w_2 work,

Then,


(x_1* n_1)/(w_1)=(x_2* n_2)/(w_2)

Here,
x_1 = 10,
n_1=22\text{ minutes},
w_1=10
x_2=14 and
w_2=14,

By substituting these values in the above equation,

We get,


(10* 22)/(10)=(14n_2)/(14)


\implies (2200)/(10)=n_2


\implies 22=n_2

Hence, the time taken by 14 workers making 14 walls is 22 minutes.

User JahMyst
by
8.1k points