A construction crew has just built a new road. it took them 7 weeks to build 8.75 kilometers of road. at what rate did they build the road?
asked
Mar 7, 2018
158k
views
2
votes
A construction crew has just built a new road. it took them 7 weeks to build 8.75 kilometers of road. at what rate did they build the road?
Mathematics
high-school
Willasaywhat
asked
by
Willasaywhat
6.7k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
5
votes
7 weeks = 8.75
1 week = x
where x is the kilometers of road built in a week
Proportion:
8.75/7 = x/1
7x=8.75
x=1.25
Fijter
answered
Mar 12, 2018
by
Fijter
6.9k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
7.4m
questions
9.9m
answers
Other Questions
How do you estimate of 4 5/8 X 1/3
Please solve the following equation. x-6x=56
whats the most accurate estimation of 65+77
Find the additive inverse of 18/23
What is 25% of 500.00
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org