Work the following pricing problems for services rendered. (Round to hundredths.) Labor rate = $7.00 per hour Labor time = 15 hours Overhead rate = 110% Retail price of parts = $38.75 Total job cost? -
asked
Jan 24, 2018
214k
views
5
votes
Work the following pricing problems for services rendered. (Round to hundredths.)
Labor rate = $7.00 per hour
Labor time = 15 hours
Overhead rate = 110%
Retail price of parts = $38.75
Total job cost?
- 133.25
- 154.25
- 259.25
- 301.88
Mathematics
high-school
Bbrame
asked
by
Bbrame
7.7k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
3
votes
Answer:
133.25
Explanation:
Ronnel
answered
Jan 26, 2018
by
Ronnel
7.7k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
6
votes
Given:
Labor rate = $7.00 per hour
Labor time = 15 hours
Overhead rate = 110%
Retail price of parts = $38.75 Total job cost = ( labor rate x labor time)( overhead rate) + retail price = ( $ 7 per hr x 15 hrs)( 1.10) + $ 38.75
= $ 154.25
Mazel Tov
answered
Jan 31, 2018
by
Mazel Tov
8.6k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.5m
questions
12.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Write words to match the expression. 24- ( 6+3)
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org