Why is it generally good for businesses if their projects end on time and with only a little money left in the budget? A)Because it indicates that their managers are competent at estimating budgets and maintaining schedules. B)Because if you finish early and with budget left over, the company will cut back on your next project. C)Because otherwise the government will think they are hiding revenue. D)Because it means their projects were over allocated.

User Reylin
by
5.4k points

2 Answers

6 votes

Answer:

A

Step-by-step explanation:

User Barnee
by
5.5k points
3 votes
A) Because it indicates that their managers are competent at estimating budgets and maintaining schedules.