184k views
4 votes
Newhard Company assigns overhead cost to jobs on the basis of 115% of direct labor cost. The job cost sheet for Job 313 includes $29,710 in direct materials cost and $10,600 in direct labor cost. A total of 1,750 units were produced in Job 313. Required: a. What is the total manufacturing cost assigned to Job 313? b. What is the unit product cost for Job 313?

User Gretchen
by
5.0k points

1 Answer

9 votes

Answer:a.Total manufacturing costs for Job 313 =$52,500

Unit Product Cost for Job 313=$30

Step-by-step explanation:

Total manufacturing costs=Direct materials+Direct labor costs+Overhead costs

But Overhead cost =115% of direct labor cost

= 115% x $10,600

=$12,190

Total manufacturing costs =$29,710 + $10,600+$12,190

=$52,500

Unit Product Cost=Total Manufacturing costs/ Total Number of Units Produced =$52,500 /1,750 units

=$30

User Divyesh Savaliya
by
4.3k points